 White Rock Lake began to collect silt from the day the dam was 
                completed. In 1933, a news article advocating dredging the lake 
                recalled that "we are able to look back to the days when the 
                lake extended a quarter of a mile north of the Northwest Highway." 
                Several years later, the first dredging of the lake got off to a 
                rocky start in 1937 (photo left).A 
                dredge was purchased by the city for $21,973 and named after Mayor 
                Joe Lawther (photo right). A few days after it began operations, 
                it sunk. Rumors flew about the drunkenness of the crew, but the 
                real cause was leaks in the hull. The dredge was raised, repaired 
                and dredging began again in
White Rock Lake began to collect silt from the day the dam was 
                completed. In 1933, a news article advocating dredging the lake 
                recalled that "we are able to look back to the days when the 
                lake extended a quarter of a mile north of the Northwest Highway." 
                Several years later, the first dredging of the lake got off to a 
                rocky start in 1937 (photo left).A 
                dredge was purchased by the city for $21,973 and named after Mayor 
                Joe Lawther (photo right). A few days after it began operations, 
                it sunk. Rumors flew about the drunkenness of the crew, but the 
                real cause was leaks in the hull. The dredge was raised, repaired 
                and dredging began again in  April 1938 and continued until February 
                1939 when operations were curtailed due to lack of funds. Shortly 
                after that, the dredge sank again. The third time was a charm and 
                the dredging operation continued for three years. The silt was used 
                to fill the swampy areas around the lake shore. The dredging project 
                added 90 acres at the north end of the lake and 60 acres at Dixon's 
                Branch Creek.
April 1938 and continued until February 
                1939 when operations were curtailed due to lack of funds. Shortly 
                after that, the dredge sank again. The third time was a charm and 
                the dredging operation continued for three years. The silt was used 
                to fill the swampy areas around the lake shore. The dredging project 
                added 90 acres at the north end of the lake and 60 acres at Dixon's 
                Branch Creek. 
              The 
                lake was dredged for the second time in 1955-56 during the drought. 
                The city did not have much money. The dredge cleaned up some on 
                the shallow water problems, then sank and rotted.
               A 
                campaign to dredge the lake again began in the late 1960s. The lake 
                level was low in 1970 and the Park Department decided that one way 
                to help get rid of silt was to encourage people to haul it off (photo). 
                Park Director L. B. Houston said "They can remove it by buckets, 
                trucks, trailers, wheelbarrows or whatever. ...About two feet of 
                top soil is available in some areas, particularly on the north end 
                of the lake. Signs will be placed in strategic locations denoting 
                'Free Dirt.'"
A 
                campaign to dredge the lake again began in the late 1960s. The lake 
                level was low in 1970 and the Park Department decided that one way 
                to help get rid of silt was to encourage people to haul it off (photo). 
                Park Director L. B. Houston said "They can remove it by buckets, 
                trucks, trailers, wheelbarrows or whatever. ...About two feet of 
                top soil is available in some areas, particularly on the north end 
                of the lake. Signs will be placed in strategic locations denoting 
                'Free Dirt.'"
               A 
                third dredging commenced in 1974 and was completed in seven months. 
                A few thousand cubic yards of silt were pumped to settling ponds 
                on the west side of White Rock Creek, north and south of the Mockingbird 
                Bridge (photo). The dog park is now on part of this landfill. The 
                rest of the silt was just pumped from the shallowest areas of the 
                lake to deeper areas through a spoil pipe running about 100 yards 
                from the position of the dredge.
A 
                third dredging commenced in 1974 and was completed in seven months. 
                A few thousand cubic yards of silt were pumped to settling ponds 
                on the west side of White Rock Creek, north and south of the Mockingbird 
                Bridge (photo). The dog park is now on part of this landfill. The 
                rest of the silt was just pumped from the shallowest areas of the 
                lake to deeper areas through a spoil pipe running about 100 yards 
                from the position of the dredge.
              The contractor was supposed to achieve an average depth of 8 feet. 
                On several occasions, the dredging crew failed to move the spoil 
                pipe. At least three islands built up to within a foot or two of 
                the water surface. Sailors placed stakes on these navigation hazards 
                and forced a meeting with the City, the engineering firm and prime 
                contractor. The dredge had been removed by this time. The engineers 
                stoutly denied that there was a problem and refused to come out 
                and see the evidence. 
               A 
                reporter for the Dallas Morning News agreed to cover the 
                story with a photographer, but his editor refused to allow him to 
                do the story. He referred the sailors to a reporter for the Dallas 
                Times Herald who had no problem with his editor. The Dallas 
                Times Herald published an article with this photo of a Butterfly 
                sailor (Bob Biegler) being pushed off a mud bank near Winfrey Point 
                by another sailor (John Diggins) standing in knee deep water. As 
                a result of the publicity, the contractor put a workboat back on 
                the lake which dragged a steel I-beam over the shallow areas until 
                they were deep enough for the sailboats.
A 
                reporter for the Dallas Morning News agreed to cover the 
                story with a photographer, but his editor refused to allow him to 
                do the story. He referred the sailors to a reporter for the Dallas 
                Times Herald who had no problem with his editor. The Dallas 
                Times Herald published an article with this photo of a Butterfly 
                sailor (Bob Biegler) being pushed off a mud bank near Winfrey Point 
                by another sailor (John Diggins) standing in knee deep water. As 
                a result of the publicity, the contractor put a workboat back on 
                the lake which dragged a steel I-beam over the shallow areas until 
                they were deep enough for the sailboats. 
               
 
 
              
 
 
              The most recent dredging (photos above) was completed in 1998. 
                All went well this time. The contractor 
                did a great job - completing the job ahead of schedule and removing 
                more silt than planned. The lake was dredged to a minimum depth 
                of 8 feet, north from a line between Winfrey Point and Jackson's 
                Point up to the Mockingbird Bridge. The spoils were pumped 17 miles 
                to an old gravel quarry in south Dallas County. A 
                dry summer combined with the dredging operation caused the water 
                level to drop to a point that sailors were unable to launch boats 
                from their davits by summer's end. Fall rains refilled 
                the lake and we were again enjoying the use of the entire lake.